[Dec-2023] Exam Sure Pass PMI Certification with PMI-RMP exam questions [Q38-Q56]

Rate this post

[Dec-2023] Exam Sure Pass PMI Certification with PMI-RMP exam questions

Real PMI PMI-RMP Exam Questions Study Guide

PMI-RMP (PMI Risk Management Professional) Certification Exam is a globally recognized certification awarded by the Project Management Institute (PMI) to professionals who demonstrate expertise in the field of risk management. PMI Risk Management Professional certification is ideal for individuals who are responsible for identifying, analyzing, and managing risks in projects and organizations. The PMI-RMP certification exam tests candidates on their knowledge and skills related to risk management principles, concepts, and techniques. It is designed to validate the candidate’s ability to assess and mitigate risk, and enhance project success.

 

NEW QUESTION 38
Which of the following is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold?

 
 
 
 

NEW QUESTION 39
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?

 
 
 
 

NEW QUESTION 40
You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

 
 
 
 

NEW QUESTION 41
Harry is the project manager of the MMQ Construction Project. In this project, Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project’s deadline. Management asked Harry to find a supplier who can fulfill the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?

 
 
 
 

NEW QUESTION 42
You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

 
 
 
 

NEW QUESTION 43
You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?

 
 
 
 

NEW QUESTION 44
John works as a project manager for ABD project. He and his team, are working on the following activities:
Relative ranking or priority list of project risks Watchlists of low priority risk Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?

 
 
 
 

NEW QUESTION 45
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?

 
 
 
 

NEW QUESTION 46
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?

 
 
 
 

NEW QUESTION 47
Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

 
 
 
 

NEW QUESTION 48
The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

 
 
 
 

NEW QUESTION 49
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?

 
 
 
 

NEW QUESTION 50
ww Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

 
 
 
 

NEW QUESTION 51
Harry is a project manager of a software development project. In the early stages of planning, he and the stakeholders operated with the belief that the software they were developing would work with their organization’s current computer operating system. Now that the project team has started developing the software it has become apparent that the software will not work with nearly half of the organization’s computer operating systems. The incorrect belief Harry had in the software compatibility is an example of what in project management?

 
 
 
 

NEW QUESTION 52
You are the project manager for your organization. You have identified a risk event you’re your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor’s solution?

 
 
 
 

NEW QUESTION 53
What best describes the job of a risk owner?

 
 
 
 

NEW QUESTION 54
A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project’s key stakeholders.
What is the first resource the project manager should reference?

 
 
 
 

NEW QUESTION 55
You are the project manager of the GYH project for your organization. Management has asked you to begin identifying risks and to use an information gathering technique. Which one of the following risk identification approaches is an information gathering technique?

 
 
 
 

NEW QUESTION 56
You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

 
 
 
 

PMI-RMP certification exam is a comprehensive assessment of a candidate’s knowledge and skills in the field of risk management. It tests the candidate’s ability to identify, assess, and mitigate risks in a project environment. PMI-RMP exam covers various topics such as risk identification, risk analysis, risk response planning, risk monitoring, and communication management. PMI Risk Management Professional certification is highly valued by employers as it demonstrates a candidate’s commitment to risk management best practices and their ability to handle complex project risks.

 

Updated and Accurate PMI-RMP Questions for passing the exam Quickly: https://www.premiumvcedump.com/PMI/valid-PMI-RMP-premium-vce-exam-dumps.html