[Jul-2023 Newly Released] Pass PMP Exam – Real Questions & Answers [Q138-Q161]

Rate this post

[Jul-2023 Newly Released] Pass PMP Exam – Real Questions and Answers

Pass PMP Review Guide, Reliable PMP Test Engine

The PMP exam is designed to test a project manager’s ability to apply project management knowledge and skills in real-world scenarios. PMP exam content is based on the Project Management Body of Knowledge (PMBOK) guide, which is a globally recognized standard for project management practices. PMP exam covers five domains: initiating, planning, executing, monitoring and controlling, and closing. PMP exam consists of 180 multiple-choice questions that must be completed in four hours. To be eligible for the exam, candidates must have a minimum of three years of project management experience, with at least 4,500 hours of leading and directing projects, and 35 hours of project management education.

PMI PMP certification exam is updated periodically to reflect the current trends and best practices in project management. The latest version of the exam, the PMI PMP (Project Management Professional (2022 Version)) Certification Exam, is designed to test the knowledge and skills required for project managers to succeed in today’s dynamic and complex business environment. The new exam includes new topics such as agile and hybrid methodologies, stakeholder management, and benefits realization management.

 

NEW QUESTION 138
During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder’s engagement?

 
 
 
 

NEW QUESTION 139
Budgets reserved for unplanned changes to project scope and cost are:

 
 
 
 

NEW QUESTION 140
Cost aggregation, reserve analysis, funding limit reconciliation, and parametric estimating are tool/ techniques of which process?

 
 
 
 
 

NEW QUESTION 141
You have been directed to establish a change control system for your company, but must convince your colleagues to use it. To be effective, the change control system must include______________.

 
 
 
 

NEW QUESTION 142
During a project, several risks are identified. The project manager wants to determine what risks will have the most potential impact. What should the project manager use to determine this?

 
 
 
 

NEW QUESTION 143
The primary communication skills you will use in working with your project sponsor will be:

 
 
 
 

NEW QUESTION 144
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

 
 
 
 

NEW QUESTION 145
As the leader of a project team, the project manager may be required to assess the competencies of his or her team members. Occasionally, some weaknesses or areas for improvement will be identified. The project manager should:

 
 
 
 

NEW QUESTION 146
A new project manager was assigned to a project during implementation The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information What should the project manager have done to avoid this?

 
 
 
 

NEW QUESTION 147
Your project is now under way, and you are working with your team to prepare your requirements management plan. Which of the following strongly influences how requirements are managed?

 
 
 
 

NEW QUESTION 148
Which of the following is an input of the Define Activities process?

 
 
 
 

NEW QUESTION 149
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery How should the project manager avoid this situation in the future?

 
 
 
 

NEW QUESTION 150
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

 
 
 
 

NEW QUESTION 151
There have been several rounds of layoffs at your company. Now your project team is worried about their job security, and you’ve noticed that their performance has decreased significantly because of it. This is predicted by which motivational theory?

 
 
 
 

NEW QUESTION 152
Which of the following best describes the following organizational structure? Exhibit:

 
 
 
 
 

NEW QUESTION 153
The process for performing variance analysis may vary, depending on:

 
 
 
 

NEW QUESTION 154
Douglas McGregor’s Theory Y advocates that the average worker:

 
 
 
 
 

NEW QUESTION 155
An organization is transitioning to an agile approach. At the project’s first sprint review, the product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?

 
 
 
 

NEW QUESTION 156
During a project, some products are acquired. The buyer and seller have agreed on a cost plus fixed fee (CPFF) contract. However, the project manager is concerned about the risks posed to the buyer associated with this type of contract.
Which contract type should have been used to lower risk for the buyer?

 
 
 
 

NEW QUESTION 157
Your spouse works for a vendor and the vendor bidding on a project at your company. You are not affiliated with the specific project team evaluating bids but you are part of the executive project management team. What do you do?

 
 
 
 

NEW QUESTION 158
A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials What should the project manager do next?

 
 
 
 

NEW QUESTION 159
Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

 
 
 
 
 

NEW QUESTION 160
Another name for an Ishikawa diagram is:

 
 
 
 

NEW QUESTION 161
During project planning, the project manager wants to transfer as many cost overrun risks as possible to the supplier What type of contract should the project manager use’?

 
 
 
 

100% Free PMP Daily Practice Exam With 570 Questions: https://www.premiumvcedump.com/PMI/valid-PMP-premium-vce-exam-dumps.html